Energiekontor AG: Weather-related construction delays lead to profit postponement

Energiekontor AG / Key word(s): Profit Warning/Change in Forecast
Energiekontor AG: Weather-related construction delays lead to profit postponement

18-Dec-2019 / 15:09 CET/CEST
Disclosure of an inside information acc. to Article 17 MAR of the Regulation (EU) No 596/2014, transmitted by DGAP - a service of EQS Group AG.
The issuer is solely responsible for the content of this announcement.


Due to significant weather-related construction delays, it is currently highly probable that a wind farm of Energiekontor AG, which is decisive for the level of consolidated EBT 2019 and is still under construction, can no longer be completed and commissioned on schedule by the end of 2019. Although every effort will continue to be made to complete the wind farm, there is a very high probability that the Group EBT of around EUR 10 million forecasted for 2019 will therefore not be achieved and, from today's perspective, will in all probability only be in the lower single-digit million euro range. The pro rata earnings contribution not realized due to the construction delay is thus postponed until next year and increases the Group EBT 2020.


Contact:
Peter Alex
Head of Investor Relations

Energiekontor AG
Mary-Somerville-Straße 5
28359 Bremen
Germany

Tel.: +49 421-3304-126
Fax: +49 421-3304-444
ir@energiekontor.com

Information and Explanation of the Issuer to this News:

When implementing a wind farm project, postponements are part of day-to-day business. The windy fourth quarter is particularly susceptible to this.

The wind farm Waldfeucht, located in North Rhine-Westphalia west of Heinsberg not far from the Dutch border, is currently under construction. Originally, the three Nordex wind turbines, each with an output of 4.5 MW per year and an expected yield of around 35 million kilowatt hours, were expected to be commissioned in December 2019. In recent weeks, high wind speeds with strong gusts have ensured that work at the site could not be carried out as planned and that delays occurred as a result. Despite countermeasures such as the request for additional erection cranes and the introduction of a three-shift operation, the prospects for completion by the end of the year have become even gloomier. For the next few days, difficult wind conditions are expected at the Waldfeucht site, which will lead to further delays.

From today's perspective, the wind farm is therefore not expected to be fully commissioned until January 2020. The earnings contribution planned for 2019 will thus be postponed until the first quarter of 2020.


18-Dec-2019 CET/CEST The DGAP Distribution Services include Regulatory Announcements, Financial/Corporate News and Press Releases.
Archive at www.dgap.de



show this

Interview im Fokus

Mountain Alliance: „Großer Digitalisierungsschub“

Furioses Börsendebüt für den Datenbankspezialisten Exasol. Einer der Profiteure: Die Münchner Beteiligungsgesellschaft Mountain Alliance AG (MA, ISIN DE000A12UK08), die auch nach einem Teilexit noch rund 2% an Exasol hält. Aktuell notiert die MA-Aktie rund 30 % unter dem NAV. Financial.de sprach mit MA-CEO Daniel Wild über die stärksten Digitalisierungstrends, die kritische Größe von 100 Mio. Euro Börsenwert, den neuen Investor und weitere Aktienkäufe.

GBC-Fokusbox

Aves One AG: Kursziel 13,60 €

Die Aves One AG ist auch in der Corona-Krise als Bestandshalter von langlebigen Logistik-Assets mit langfristigen Mietverträgen gut aufgestellt. Das Unternehmen hat als Guidance einen Umsatz und ein EBITDA mindestens auf Vorjahresniveau verkündet. Unseres Erachtens sollte dies auch ohne Zukäufe gut machbar sein, da die im abgelaufenen Geschäftsjahr 2019 erworbenen Assets bereits zu einer höheren Umsatzbasis führen sollten. Auf Basis unseres DCF-Modells haben wir ein Kursziel in Höhe von 13,60 € ermittelt und vergeben ein KAUFEN-Rating.

News im Fokus

Continental AG: Die Continental AG hat beschlossen, den Gewinnverwendungsvorschlag für die Hauptversammlung am 14. Juli 2020 auf 3,00 Euro pro Aktie anzupassen

03. Juni 2020, 11:28

Aktuelle Research-Studie

Original-Research: UMT AG (von Montega AG): Kaufen UMT AG

03. Juni 2020